Serving Burleson, Fort Worth & the southwest Metroplex
Texas Best Demolition Demolition & Dirt Work · Burleson TX
Two excavators working a demolition site side by side
Call (817) 564-4360 Get a Free Quote

Do You Need a Permit to Demolish a House in Fort Worth?

Yes. Fort Worth requires a wrecking and razing permit through Development Services before a structure comes down. A separate permit is required for each address and each structure being demolished. You apply online or in person at Development Services, 200 Texas Street, Lower Level. The city’s residential permitting page says the removal of a building from your property requires a permit.

The paperwork sets the schedule more than the machine does. The application wants a marked site plan, the exact square footage and a signed indemnification form. We file the wrecking permit as part of a house demolition job in Fort Worth. The estimate comes first, priced at the property, free.

What does the Fort Worth wrecking permit application ask for?

The checklist asks for a site plan or survey of the property, marked to show which structure is being razed. It wants the exact square footage of the structure coming down. A contractor registration number goes on the form. A residential property owner can skip that number by showing proof of ownership.

A Wrecking Indemnification form comes with it, and the agreement on that form cites City Ordinance No. 7314. The form also splits residential from commercial. The residential side lists Single Family, Duplex, Townhouse and Accessory Structure, and apartments are considered commercial property.

What the application needsWho supplies itSource
One permit per address and per structureThe applicant, one form eachFort Worth wrecking and razing checklist
Site plan or survey marked to the structure being razedProperty owner or contractorFort Worth wrecking and razing checklist
Exact square footage of that structureProperty owner or contractorFort Worth wrecking and razing checklist
Contractor registration number, or proof of ownership insteadThe contractor, or a residential property ownerFort Worth wrecking and razing checklist
Signed Wrecking Indemnification form (City Ordinance No. 7314)The applicantFort Worth wrecking and razing checklist
Residential type: Single Family, Duplex, Townhouse or Accessory StructureMarked on the applicationFort Worth wrecking and razing checklist
Asbestos notification 10 working days before the start dateFiled with Texas DSHS where the rules applyTexas DSHS
Street use permit when a dumpster or truck sits in the streetThe demolition contractorCity of Fort Worth

Online submittals run through Accela. In person, the counter sits at 200 Texas Street, Lower Level. The same residential permitting page that covers a teardown also puts a permit on demolition of interior walls.

Do you need an asbestos survey before a demolition in Texas?

For one private residence, usually not. Texas DSHS says one private residence being demolished is not subject to the asbestos NESHAP regulations. No notification is required for that house. The federal rule covers demolitions of facilities and excludes residential buildings with four or fewer dwelling units.

The exemption is narrow. EPA does not treat a house as exempt when it is demolished as part of a commercial or public project. A teardown folded into a larger retail and warehouse demolition project can land back under the rule.

Where NESHAP applies, the work starts with paper. The rule requires a thorough inspection of the area where the demolition will occur. A survey comes before a covered building is torn down. In Texas that survey is done by a licensed asbestos inspector or consultant. The state’s public-building rules also require licensed people to remove the asbestos.

The notice has its own clock. 40 CFR 61.145 sets the demolition notification at 10 working days before demolition begins. Texas counts 10 working days, not calendar days, before the project start date under rule 295.61. That notification goes to DSHS even when no asbestos is present.

Age is the tell on an older house. Homes built before 1980 can hold asbestos in siding or old floor tile. We are a demolition and dirt-work contractor, not an abatement contractor. A survey and licensed abatement come first where the rules require them.

What about a garage, shed, barn or mobile home?

Every structure gets its own permit. The checklist says separate permits are required for each address and each structure being demolished. It also asks which structure is being razed when a lot holds several. A detached garage, shed or barn is filed on its own as an Accessory Structure.

Fort Worth’s residential permits cover one- and two-family detached homes and their accessory structures on individually platted lots. So a house and a shop on the same lot are two permits and two square-footage numbers. We file them together and tear down detached garages and barns on the same trip.

Single-wides and double-wides are their own structure, and mobile home demolition and removal carries the same permit question. A swimming pool is its own job as well, and pool removal cost ranges sit in a separate guide.

Putting a building back needs a permit too. Fort Worth requires a building permit for any accessory structure, storage buildings included. Zoning rules there set the location, the height and the square footage.

How much does a demolition permit cost in Fort Worth?

The city’s wrecking and razing checklist does not print a fee. The amount comes from the permit desk for your address. National guides keep the figure small. Fixr’s house demolition guide says permits begin at around $100, and the pool removal guides from HomeAdvisor and Fixr put pool removal permits at $50 to $250.

Cities nearby publish their own numbers. Arlington’s fee schedule effective June 1, 2026 lists a demolition permit at $200 per building.

One more permit shows up on a tight lot. A Fort Worth Temporary Street Use Permit covers a dumpster or truck parked in the street. It takes 3 to 5 business days and costs $112.50. That lead time is the reason the street question gets asked at the estimate.

The demolition itself is the real number. Fixr puts house demolition at a national average range of $7,500 to $15,000. Fixr’s national average is $10,000 for mechanical demolition of a 1,500 square foot slab home, and its partial demolition range runs $1,000 to $20,000. Our Fort Worth house teardown cost guide works through what moves those numbers.

Published ranges are not a quote. A real price needs someone standing on the property with the house in front of them.

What happens to the utilities before the teardown?

They come off first. Gas, electric, water and sewer each need to be disconnected and verified by the provider before a teardown. That step usually sets the start date. Each provider runs on its own schedule, so those requests go in while the permit is being filed.

Our crews confirm the electric is pulled and the gas and water lines are capped. Only then does a machine touch the house. The sewer gets plugged so the line stays clear once the slab comes out. A live meter stops a job on the spot.

This is the step that moves start dates. A house can sit ready for days waiting on one disconnect.

What if the house is in Burleson, Joshua, Arlington or the county?

The desk changes with the address. Burleson lists demolition of a building among the projects that require a permit. Its building permit application carries Demolition as a class of work, and the city’s Building Permit and Inspection Department issues it. Inside Joshua city limits, the city handles demolition permits through its development services office on South Main Street.

In unincorporated Johnson County, the county handles development and floodplain items. Arlington, Mansfield, Grand Prairie and the other cities run their own permit desks. We check which authority covers the address before a date goes on the schedule.

Growth keeps pushing this question outward. Johnson County grew 21.1 percent and Burleson 19.5 percent from April 2020 to July 2025, per the Census. A new subdivision and an old farmstead can sit a mile apart and answer to different desks.

Where does the debris go?

Onto our own trucks and trailers, then to a landfill or a concrete yard. Arlington Landfill is open Monday through Saturday, 7:00 to 4:30. Turkey Creek Landfill in Alvarado takes loads from 8 a.m. to 3 p.m. Monday through Saturday, and loads must be tarped. Big City Crushed Concrete takes clean concrete rubble free at its Fort Worth and Arlington yards.

Those hours shape the day more than the teardown does. A house that comes down at noon still needs loads moving before a gate closes. We run three roll-off trucks and about 75 roll-off dumpsters, plus high-side end-dump trailers pulled by road tractors.

Sorting the pile is part of the work. Clean concrete rides to the crushed-concrete yard and the rest goes to the landfill. Roll-off dumpster rental in the Fort Worth area is priced on its own when a homeowner is doing the work.

How do you get the permit and the teardown handled?

We handle the wrecking permit paperwork as part of the job. The site plan, the square footage and the indemnification form go in together. The utility disconnects get started at the same time, and the estimate comes before any of it.

Texas Best Demolition works out of Burleson. We cover demolition in Fort Worth, TX, Arlington, Mansfield, Crowley and the rest of the southwest Metroplex. About 20 people work here, and we keep 17 to 18 house demolitions moving at a time. Our excavators run from a compact Bobcat E88 up to a Kobelco 350.

Send us the address and a day that works. Someone comes out and looks at the house, the access and what sits under the slab. Then you get a number. Ask for a free demolition estimate and we will take the permit from there.

Frequently asked questions

How much is a demolition permit in Texas?
The fee comes from the city, not the state. Fixr says house demolition permits begin at around $100, and HomeAdvisor and Fixr put pool removal permits at $50 to $250. Fort Worth's wrecking and razing checklist does not print an amount. Arlington's fee schedule effective June 1, 2026 lists a demolition permit at $200 per building.
What permits do I need to demolish a house?
In Fort Worth, a wrecking and razing permit from Development Services, filed for each address and each structure. Where the asbestos rules apply, a notification goes to Texas DSHS 10 working days before the start date. A Fort Worth Temporary Street Use Permit, at $112.50, covers a dumpster or truck parked in the street.
Can a homeowner pull their own demolition permit in Fort Worth?
Yes. The wrecking application asks for a contractor registration number, and that number is not required for a residential property owner who shows proof of ownership. Residential applicants are either registered building contractors or homeowners who meet the homestead-permit rules, meaning a primary residence with a homestead exemption. Our Fort Worth house demolition service pulls the permit either way.
Do I need a permit to tear down a shed or detached garage in Fort Worth?
Yes. Separate permits are required for each structure, and a detached garage, shed or barn is filed on its own as an Accessory Structure. The site plan marks which building is coming down. Putting a new storage building back needs its own building permit. Garage, shed and barn demolition is priced the same way.
Does a demolition contractor need a license in Texas?
Fort Worth's wrecking application asks for a contractor registration number, and a residential property owner can apply with proof of ownership instead. Asbestos work is where licensing is explicit: a Texas public-building survey is done by a licensed asbestos inspector, and the rules require licensed people to remove asbestos. Ask the permit desk what your address needs.
Do I need an asbestos survey to tear down my own house?
Usually not. Texas DSHS says one private residence being demolished is not subject to the asbestos NESHAP regulations, and no notification is required. The federal rule leaves out residential buildings with four or fewer dwelling units. A house that comes down as part of a commercial or public project loses that exemption.
How long before the teardown does the asbestos notice have to be filed?
Ten working days. 40 CFR 61.145 sets the federal demolition notification at 10 working days before demolition begins, and Texas rule 295.61 counts working days rather than calendar days before the project start date. That is two full calendar weeks, and longer when a holiday lands in it. DSHS wants the notice even when no asbestos is present.
Ready to Start Your Project?

Get In Touch With Texas Best Demolition

A house or building that needs to come down, a slab or pool that needs to come out, dirt that needs to move? Call or send the form and we will look at the job with you and price the whole thing, teardown through cleanup. The estimate is free.

Get a Free Estimate

Tell us about your project and we will get right back to you.

Call (817) 564-4360